Running Project

Improvement & Development of Storm Water Drainage & Urban Road

Project : Improvement and Development of Storm Water Drainage & Urban Road Sub- Project
Contract ID : IUDP/DR/JNK/ICB-01
Employer : Janakpur Sub- Metropolitan City, IUDP, PIU, Janakpurdham, Nepal
Contract Amount : NRs. : 988,156,638.13
Contractor : ZIEC- Sharma JV.
Contract Period : 720 days

Construction of Municipal Trunk Sewer, River Training Works, Service Road with Asphalt Concreting and other Related Works, Km 2+900-6+000

Project:      Construction of Municipal Trunk Sewer, River Training Works, Service Road with

                 Asphalt concreting and Other Related Works   

 Employer : High Powered Committee for Integrated Development of the Bagmati Civilization

                     Guheshwori, Kathmandu

Contract Amount : NRs. : 621,426,030.15
Contractor : Sharma-Apex- Kanchharam JV.
Start Date : November, 2015
Completion Date : Oct., 2017

Design and Build of Mawa Khola Bridge

Project : Design and Build of Mawa Khola Bridge
Contract ID : PCU-DB-PQ-ER-071/72-22 
Employer : DOR, Bridge Branch, Lalitpur 
Contract Amount : NRs. : 302,291,750.00
Contractor : Sharma- Lama- Swachchhanda JV.
Start Date: July 2015
Contract Period : 48 months

Laying of Bulk Distribution Systems & Construction Of Service Reservoirs ( Package-2)

Project : Laying of Bulk Distribution Systems & Construction Of Service Reservoirs ( Package-2)
Contract ID : KUKL/BDS-SRT/01/02
Employer : Kathmandu Upatyaka Khanepani Limited , Anamnagar, Kathmandu, Nepal.
Contract Amount : NRs. : 2,544,874,284.09
Contractor : JWIL- SCPL JV
Contract Period : 900 days
Start Date : August 2014

Improvement & Development of Storm Water Drainage & Urban Road

Project : Improvement and Development of Storm Water Drainage & Urban Road Sub- Project
Contract ID : IUDP/DR/SDN/ICB-01
Employer : Siddhartha Municipality, IUDP, PIU, Siddharthanagar, Rupendehi, Nepal
Contract Amount : NRs. : 705,111,240.60
Contractor : China Guangzhou - Sharma JV.
Contract Period : 720 days
Start Date : Feb 2015

Upgrading of Belhiya Butuwal Road Employer Department of Road ACQMP

Project : Upgrading /widening of Belhiya - Butuwal Road (18+000 to 21+000)
Contract ID : ACQMP/TRIP/BB-02/070-071
Employer : Department of Road, ACQMP, Babarmahal, Kathmandu, Nepal.
Contract Amount : NRs. : 575,090,058.00
Contractor : Sharma-Lama- Kanchharam JV.
 Start Date : June, 2014
Revised Completion Date : Nov., 2016

Distribution Network Improvement for Efficient NRW Management Package 2

Project : Distribution Network Improvement for Efficient NRW Management – Package 2
Contract ID : KUKL/DNI/01/05
Employer : Kathmandu Upatyaka Khanepani Limited , Anamnagar, Kathmandu
Contract Amount : NRs. : 2276,772,851.84
Contractor : Hangzhou- Sharma JV
 Start Date : Nov. 2013
Contract Period : 1095 days

Construction of Hospital Building Complex for Ashwins Medical College and Hospital Pvt. Ltd.

Project : Construction of Hospital Building Complex for Ashwins Medical College and Hospital  Pvt. Ltd.
Employer :  for Ashwins Medical College and Hospital Pvt. Ltd.
Consultant :  Cage Consult Pvt. Ltd. Kathmandu.
Chief Architect : Ar. Bishnu Panthee
Contract Amount  :
Phase I :  NRs.  644,100,001.13
Phase II: NRs.   529,202,131.10
Work In progress :  96 % Completed
Completion Date : April, 2015